Lagos To Experience Partial Blackout For 8 Weeks, DISCO Gives reason - Green White Green - gwg.ng

National

Lagos To Experience Partial Blackout For 8 Weeks, DISCO Gives reason

Published

on

Ikeja Electric Plc says some area under its operational network in Lagos State will experience blackout for a period of eight weeks to enable the Transmission Company of Nigeria (TCN) re-conduct its 132KV lines.

The News Agency of Nigeria (NAN) reports that Mr Olajide Kumapayi, Chief Technical Officer, Ikeja Electric, made the announcement at a news briefing on Monday in Ikeja.

Kumapayi said the project which would begin on Oct. 11 was aimed at increasing the capacity of the transmission lines to wheel more power from the generation companies.

He noted that some of 132K lines installed over 50 years ago had become obsolete and degraded due to time and usage.

According to him, areas that will be affected by blackout include Oregun, Police Training College, Oba Akran, Oke Ira, Ogba, Magodo , Anifowoshe and Omole Phase One.

Kumapayi said: “The TCN is currently embarking on the upgrade of the 132KV lines from Ikeja West to Ota and Alimosho in stages. This is the second stage.

“The TCN is replacing all the aluminum conductors with gap conductors which is more sophisticated to withstand heat and has more capacity to carry current.

“The implication of this is that from 8 a.m. to 6 p.m. everyday, the substations controlling these areas will be switched off which will affect the feeders connected to them.

“This will affect all categories of customers within the area especially our Maximum Demand (MD) customers such as Ikeja City Mall, Police College, Lagos State University Teaching Hospital and the Ikeja High Court.”

He added that the TCN would also move to Alimosho and Agege axis of Lagos during the next stage which will also experience the blackout.

Kumapayi noted that the upgrade was a power sector initiative to boost transmission and distribution of electricity to Nigerians as he apologised to the Lagos customers for the blackout.

Also, Mr Felix Ofulue, Head, Corporate Communications, Ikeja Electric, said the DisCo had written to the MD customers in Lagos notifying them of the situation and the impending blackout.

Ofulue said the company was also meeting with its bilateral power supply agreement partners and appealed to all those affected to exercise patience with the DisCo during the period.

“Even though this is a TCN project, it is our duty to inform our customers of the situation because we are the ones that interface with them on a daily basis.

“We believe it will be for the benefit of our customers at the end of the day and will also allow Ikeja Electric to invest more in our system to improve power supply to customers under our network,” Ofulue said.

Send Us A Press Statement Advertise With Us Contact Us

 And For More Nigerian News Visit GWG.NG

Click to comment

Trending

Exit mobile version